Excel optimizer

igorsusa

Member
Hello!

Could you please help me on my problem. I dont know if the solution will be VBA code or formulae so I am posting my question here.

Please see the attached file.

Thanks.
 

Attachments

I think you need to supply more logic as to when a Rig can be used
In your example I think Rig 2 should have been introduced after ID: 24

What determines which Rig is used when both are available?
I assume it is location/distance to the next job, but that data isn't available
 
Hi Igor ,

To add to what Hui has posted , Rig 2 is available from 1-6-2015 , which means it can be put into use from ID 7 itself ; if it is introduced at this stage , then interleaving Rigs 1 and 2 means you need not have any move time of 5 days between uses , since while Rig 1 is being used for drilling , Rig 2 can be moved to where ever it is required , and vice versa.

The same principle can be extended to Rigs 3 , 4 and 5 as and when they are available to be put into use. At this stage it is governed purely by the distance between drilling locations.

Narayan
 
Hello old friend NarayanK!

Thanks to you both for your tips, I have in the meantime successefully acomplished the task! :)

Have a wonderful 2015!
 