Hi Narayan,
okay, that seems great. but i have no idea how i would do that? lol.
that really is drilling down the info.
I was going for a very simple idea. just as the data was completed in the last cell.
so if cells 1 -7 had data then just average the number in "days to production"
i...
RFQ IN RFQ OUT QUOTE In QUOTE REP JB IN JB OUT DAYS TO PRODUCTION
5/07/13 5/08/13 5/09/13 10/10/13 11/11/13 12/12/13 115
5/07/13 5/08/13 10/09/13 1/12/13 106
5/07/13 1
HI Narayan,
as above, so i wanted the...
i tried =AVERAGE(Table2[DAYS TO PROD])
which gives a false result. i would like a cumalitive result as the jobs increase. meaning as the rows fill.
wow this hard to explain!
thank you narayan, i sincerely appreciate your help.
I'll do some research on your formula to understand it better, that said i would really like to learn more about excel and look to do a course with chandoo!
where would you suggest a good place to start?
kind regards dave
Hi Narayan,
thank you for your patience, this is new to me.
there will be 1 - 7 cells with dates inputed into them.
what i wanted was one cell that calculated the time in days between the dates and gave a result of "x" days from start to end.so as the job progressed the total days would...
Hi Friends,
I'm just starting out with excel and i have researched a formula but it doesn't seem accurate its oftern a day or two out.
what i wanted to achieve was the time it takes to deliver a product from th eday the quotation took place. so i have 5 cells that have data that will show...